ライン

FASTMET® is a direct reduction process using rotary hearth furnace (RHF).
Various carbon sources such as coal, coke breeze or carbon bearing wastes can be used as reductant. Reduction process is completed in 6 - 12 minutes.


FASTMET® Plant at Kobe Steel Kakogawa Works (KDP)

ライン

Application

Ironmaking from iron ore

FASTMET® plant to be used as a core or supplemental ironmaking plant in a steel mill


High quality product, with a metallization degree of 85 - 92%, in the form of DRI (Direct Reduced Iron) or HBI (Hot Briquetted Iron), will be charged to Blast Furnace, Basic Oxygen Furnace or Electric Arc Furnace as a core or supplemental source of iron. Carbon content in DRI can be adjusted as per customer's requirement.

DRI can also be melted to produce hot metal (FASTIRONTM) via FASTMELT® process, which combines RHF with the Electric Ironmaking Furnace (EIFTM) to produce hot metal directly from hot DRI. This method provides an economical source of high purity hot metal and remarkably increases productivity for the succeeding steelmaking process.


Recycling of steel mill wastes

FASTMET® plant to be used as a steel mill waste recycling plant


Steel mill wastes such as BF dust, BF Sludge, BOF dust, Sinter dust, EAF dust, mill scale, and etc., will be processed by FASTMET® plant. Benefits from this application will be ;

Elimination of waste disposal cost and landfill liability
Waste changed to a quality source of iron (DRI)
To be recycled in iron or steel making process
Metallization degree:
Iron: 85-92%
Nickel: 95-100%
Recovery of Zinc contained in wastes (Zn deriving from scrap)
To be sold to zinc producer
Zinc removal: 95% or higher
Reclamation of carbon
Carbon contained in dusts will be used as reductant
Carbon content in DRI can be adjusted as per customer's requirement

FASTMET® Process Flow

Environment

Kobe Steel also has abundant experiences on environmental matters, such as incinerator and sewerage plants. Experiences on incinerator plant have been adopted to FASTMET® process facilities, especially to off-gas system. All the environmental restrictions such as particulate, NOx, SOx, dioxin etc. will be cleared as was done in existing FASTMET® plants.

Reference List

Client Capacity
(material processed)
Start-up
Nippon Steel
(Hirohata Works)
190,000 tpy April, 2000
Kobe Steel
(Kakogawa Works)
 16,000 tpy April, 2001
Nippon Steel
(Hirohata Works No.2)
190,000 tpy February, 2005

For more details, please contact;

Kobe Steel, Ltd.
Natural Resources & Engineering Business
Iron Unit Division
9-12, Kita-Shinagawa 5-chome, Shinagawa-ku
Tokyo 141-8688, Japan

Tel. : +81-3-5739-6635
Fax : +81-3-5739-6975



To Home of Natural Resources & Engineering | To Home of Kobe Steel, Ltd.